Category 07Project Management System

Interior Project Timeline (Gantt Chart)

7-phase Gantt chart for Indian interior projects — Client Onboarding through Final Handover. Set project size (Express 8w → Villa 24w), enter your start date, view the phase-wise schedule, and download a professional PDF timeline for client presentations.

7 Phases4 Project SizesDependency TrackingCommon Delays GuideFast-track ModePDF Export

Project Details

Project Summary

Size
Standard 2BHK / 3BHK
Total Duration
14 weeks
Start
27 Aug 2026
Target Handover
03 Dec 2026

7-Phase Schedule

#PhaseWeeksDependencyDates
1Client Onboarding & BriefW1–W1None27 Aug 202603 Sept 2026
2Concept DesignW2–W3Brief approval03 Sept 202617 Sept 2026
3Design DevelopmentW3–W5Concept freeze10 Sept 202601 Oct 2026
4BOQ & ProcurementW5–W7Design freeze24 Sept 202615 Oct 2026
5Site ExecutionW6–W12Material arrival01 Oct 202619 Nov 2026
6Installation & StylingW11–W13Civil completion05 Nov 202626 Nov 2026
7Final HandoverW13–W14QC completion19 Nov 202603 Dec 2026