Category 07Project Management System

Interior Project Timeline (Gantt Chart)

7-phase Gantt chart for Indian interior projects — Client Onboarding through Final Handover. Set project size (Express 8w → Villa 24w), enter your start date, view the phase-wise schedule, and download a professional PDF timeline for client presentations.

7 Phases4 Project SizesDependency TrackingCommon Delays GuideFast-track ModePDF Export

Project Details

Project Summary

Size
Standard 2BHK / 3BHK
Total Duration
14 weeks
Start
22 Nov 2026
Target Handover
28 Feb 2027

7-Phase Schedule

#PhaseWeeksDependencyDates
1Client Onboarding & BriefW1–W1None22 Nov 2026 → 29 Nov 2026
2Concept DesignW2–W3Brief approval29 Nov 2026 → 13 Dec 2026
3Design DevelopmentW3–W5Concept freeze06 Dec 2026 → 27 Dec 2026
4BOQ & ProcurementW5–W7Design freeze20 Dec 2026 → 10 Jan 2027
5Site ExecutionW6–W12Material arrival27 Dec 2026 → 14 Feb 2027
6Installation & StylingW11–W13Civil completion31 Jan 2027 → 21 Feb 2027
7Final HandoverW13–W14QC completion14 Feb 2027 → 28 Feb 2027