Interior Project Timeline (Gantt Chart)

7-phase Gantt chart for Indian interior projects — Client Onboarding through Final Handover. Set project size (Express 8w → Villa 24w), enter your start date, view the phase-wise schedule, and download a professional PDF timeline for client presentations.

7 Phases4 Project SizesDependency TrackingCommon Delays GuideFast-track ModePDF Export

Project Details

Project Summary

Size
Standard 2BHK / 3BHK
Total Duration
14 weeks
Start
28 May 2026
Target Handover
03 Sept 2026

7-Phase Schedule

#PhaseWeeksDependencyDates
1Client Onboarding & BriefW1–W1None28 May 202604 Jun 2026
2Concept DesignW2–W3Brief approval04 Jun 202618 Jun 2026
3Design DevelopmentW3–W5Concept freeze11 Jun 202602 Jul 2026
4BOQ & ProcurementW5–W7Design freeze25 Jun 202616 Jul 2026
5Site ExecutionW6–W12Material arrival02 Jul 202620 Aug 2026
6Installation & StylingW11–W13Civil completion06 Aug 202627 Aug 2026
7Final HandoverW13–W14QC completion20 Aug 202603 Sept 2026