Interior Project Timeline (Gantt Chart)

7-phase Gantt chart for Indian interior projects — Client Onboarding through Final Handover. Set project size (Express 8w → Villa 24w), enter your start date, view the phase-wise schedule, and download a professional PDF timeline for client presentations.

7 Phases4 Project SizesDependency TrackingCommon Delays GuideFast-track ModePDF Export

Project Details

Project Summary

Size
Standard 2BHK / 3BHK
Total Duration
14 weeks
Start
04 Oct 2026
Target Handover
10 Jan 2027

7-Phase Schedule

#PhaseWeeksDependencyDates
1Client Onboarding & BriefW1–W1None04 Oct 2026 → 11 Oct 2026
2Concept DesignW2–W3Brief approval11 Oct 2026 → 25 Oct 2026
3Design DevelopmentW3–W5Concept freeze18 Oct 2026 → 08 Nov 2026
4BOQ & ProcurementW5–W7Design freeze01 Nov 2026 → 22 Nov 2026
5Site ExecutionW6–W12Material arrival08 Nov 2026 → 27 Dec 2026
6Installation & StylingW11–W13Civil completion13 Dec 2026 → 03 Jan 2027
7Final HandoverW13–W14QC completion27 Dec 2026 → 10 Jan 2027