Interior Project Timeline (Gantt Chart)

7-phase Gantt chart for Indian interior projects — Client Onboarding through Final Handover. Set project size (Express 8w → Villa 24w), enter your start date, view the phase-wise schedule, and download a professional PDF timeline for client presentations.

7 Phases4 Project SizesDependency TrackingCommon Delays GuideFast-track ModePDF Export

Project Details

Project Summary

Size
Standard 2BHK / 3BHK
Total Duration
14 weeks
Start
13 Jul 2026
Target Handover
19 Oct 2026

7-Phase Schedule

#PhaseWeeksDependencyDates
1Client Onboarding & BriefW1–W1None13 Jul 202620 Jul 2026
2Concept DesignW2–W3Brief approval20 Jul 202603 Aug 2026
3Design DevelopmentW3–W5Concept freeze27 Jul 202617 Aug 2026
4BOQ & ProcurementW5–W7Design freeze10 Aug 202631 Aug 2026
5Site ExecutionW6–W12Material arrival17 Aug 202605 Oct 2026
6Installation & StylingW11–W13Civil completion21 Sept 202612 Oct 2026
7Final HandoverW13–W14QC completion05 Oct 202619 Oct 2026