Studio Matrx Monthly · Volume 1 · Issue 3 · August 2026
Amogh N P
 In loving memory of Amogh N P — Architect · Designer · Visionary 
Design Stages & DeliverablesLesson 5.2
APM for Architecture, Planning & Urban Design/Module 5 · Services & Project Stages

Lesson 5.2 · Services & Project Stages

Design Stages & Deliverables

From brief and concept to developed and detailed design - what you produce, who coordinates, and how approvals run in parallel

14 min Interactive lessonFree · open lessonByAmogh N P· Architect & interior designer
The hook

The design isn't one drawing - it's a hundred decisions in order

A finished building looks like a single confident idea, but it is really the settled residue of hundreds of decisions taken in a deliberate order: first the big move, then the arrangement, then the systems, then the joints. The design stages are the machinery that takes those decisions in the right sequence, coordinates them across a team of consultants, and gets each one signed off before it hardens - so that by the time you document the building, almost nothing is still an open question.

Freeze the design and the whole project stops shivering.

Brief to concept

From the brief to the concept: the big move

Design proper begins where the brief ends. The brief - covered fully in Module 4 - tells you what the client needs, how much they can spend, what the site allows and what the authorities require. The concept, or schematic, stage answers the first design question: what is the overall idea that satisfies all of that? Here you work at the scale of the whole: how the building sits on the site, how it is oriented for sun and wind, how the major spaces are arranged and related, how tall and how deep it is, and what its essential character will be. In Indian practice this is the concept or preliminary design stage; in RIBA it is Stage 2; in AIA it is Schematic Design.

The deliverables at this stage are deliberately economical: a site plan, general-arrangement plans of each level, one or two sections, an elevation or a massing view, perhaps a simple physical or digital model, and a short design narrative that explains the thinking. The drawings are usually at a coarse scale - 1:200 or 1:100 for a building of moderate size - because their job is to communicate the idea and win agreement, not to build from. A common beginner's error is to over-render the concept, polishing materials and details that will change, when the client only needs to understand and approve the direction.

The concept stage also carries the first honest cost check. A concept that cannot be built within the budget is not a concept; it is a fantasy. Even a rough area-and-rate estimate at this stage, checked against the client's figure, saves everyone from developing a scheme that will have to be gutted later. Better to confront the budget while the design is still cheap to change.

Design resolves from coarse to fineCONCEPTDEVELOPEDDETAILEDthe big movemake it hold togetherhow it is madesite planGA plans 1:200/100a section, massingdesign narrativefirst cost checkdimensioned plans 1:100structural strategymaterials + systemsMEP coordinationoutline spec + costjunction details 1:20/5wall/roof/windowwaterproofingspecialist packagesnothing left openclient sign-offsign-off + FREEZEready to documentdrawings sharpen; open questions closeScales shown are indicative and vary with building size.
Zoom
Escalating resolution across the design stages. Concept delivers economical, coarse-scale drawings to win the direction; developed design fixes dimensions, structure and systems and coordinates the team, then freezes; detailed design resolves the junctions and specialist elements. Each gate closes with a recorded client sign-off.

Do not polish the concept - the client is buying the direction, not the varnish.

The client gate

Winning the concept sign-off

The concept stage closes with the single most important approval on the project: the client agreeing the design direction. Everything downstream assumes this is settled, so the sign-off must be real, not a polite nod. That means presenting the concept in a way a non-designer can genuinely understand - plain plans, a clear section, a simple view, and a narrative in ordinary language - and drawing out the client's true reaction rather than their courtesy. A client who murmurs approval in the meeting and then, three weeks later, reveals they always hated the double-height space has cost you a stage.

Good practice makes the concept sign-off explicit and recorded. You present, you discuss, you incorporate reasonable comments, and then you obtain a clear approval - ideally in writing, even a confirming email - that the client is happy for you to develop this scheme. This record is what protects you later: when a change arrives at detailed design, the signed concept is the baseline against which it is visibly a change.

This is also where you manage the client's expectations about change itself. Explain, warmly but plainly, that the concept stage is the cheap place to change their mind - move the staircase now, not after the services are coordinated around it. Encourage them to interrogate the scheme hard while it is still fluid. Paradoxically, inviting challenge at the concept gate reduces disruptive change later, because the client feels heard and the big questions are genuinely resolved before the design hardens. The gate is not a formality; it is the hinge on which the whole programme swings.

The concept gate is the cheap place to change your mind.

Developed design

Developed design: making the idea hold together

Once the concept is signed off, the scheme enters developed design - RIBA Stage 3, AIA Design Development, the Indian design-development or scheme-design stage. The question shifts from what is the idea to does the idea actually hold together. Now you fix dimensions, choose the structural strategy, select the principal materials and systems, resolve the sections properly, and confirm that spaces work at a human scale. The drawings advance in resolution - typically to 1:100 and 1:50 for key areas - and gain the information a coordinated scheme needs: grids, levels, principal dimensions, an outline specification of materials and systems.

The defining activity of this stage is coordination. A building is not just architecture; it is architecture wrapped around structure, mechanical and electrical services, plumbing, and increasingly data and controls. During developed design the architect works with the structural and services engineers so that beams, ducts, shafts, tanks and plant all have a place that does not wreck the architecture - the ceiling is high enough after the ducts, the column does not land in the middle of the room, the plant room is big enough and in the right place. Catching these clashes on paper, or in a coordinated model, is vastly cheaper than catching them on site.

The deliverable at the end of developed design is a coordinated, dimensioned scheme with materials and systems selected, an outline specification, and an updated cost check against the budget. Crucially, this is where the design is meant to freeze. After this stage, changes become genuinely expensive because they ripple through structure, services and documentation. A disciplined practice pushes hard for a design freeze at the end of developed design and treats anything later as a formal variation.

Design resolves from coarse to fineCONCEPTDEVELOPEDDETAILEDthe big movemake it hold togetherhow it is madesite planGA plans 1:200/100a section, massingdesign narrativefirst cost checkdimensioned plans 1:100structural strategymaterials + systemsMEP coordinationoutline spec + costjunction details 1:20/5wall/roof/windowwaterproofingspecialist packagesnothing left openclient sign-offsign-off + FREEZEready to documentdrawings sharpen; open questions closeScales shown are indicative and vary with building size.
Zoom
Escalating resolution across the design stages. Concept delivers economical, coarse-scale drawings to win the direction; developed design fixes dimensions, structure and systems and coordinates the team, then freezes; detailed design resolves the junctions and specialist elements. Each gate closes with a recorded client sign-off.
Detailed design

Detailed design: how it is actually made

Detailed, or technical, design - RIBA Stage 4, part of the run toward AIA Construction Documents - answers the finest design question: exactly how is each part of the building made and put together? Here you resolve the junctions and details that a coordinated scheme still leaves open: how the roof meets the wall, how the window sits in its opening and keeps water out, how the waterproofing turns up at the parapet, how the balcony is drained, how the finishes meet at a threshold. This is where much of a building's quality and durability is actually decided - a beautiful concept ruined by a leaking parapet is a common and avoidable tragedy.

Detailed design also draws in the specialist and contractor-designed elements. Many components - facade systems, lifts, structural steel connections, complex MEP plant - are designed in detail by specialist subcontractors or suppliers, within a performance specification the architect and engineers set. Part of the architect's job at this stage is to specify those performance requirements clearly, to review and coordinate the specialists' proposals when they come, and to make sure everything still adds up to the intended building. In India this coordination stretches across a mix of formal consultants and less formal trade contributions, and the architect's coordinating discipline matters all the more.

Because the boundary between detailed design and documentation is porous, many practices run them together: the detailed design decisions are captured directly in the construction drawings and specifications that Lesson 5.3 covers. What matters conceptually is that by the end of this stage there should be no significant design questions left open - only the production task of drawing and specifying everything completely enough to price and build.

A building's durability lives in its junctions - resolve them on paper.

Approvals in parallel

The approvals track running alongside

While the design stages proceed, a second track runs in parallel and often lags or leads them awkwardly: statutory approvals. In Indian practice a set of sanction or building-permit drawings must go to the local municipal authority for approval, usually prepared around the end of concept or during developed design, and drawn to the authority's specific format showing compliance with the development-control and building rules, coverage, floor-area ratio, setbacks, heights and parking. Alongside the building sanction sit other clearances - fire from the fire service, environmental clearance for larger projects, airport-height where relevant, and various utility and infrastructure no-objection certificates.

The hard truth is that these approvals run on their own clock and can dominate the programme. A scheme can be fully coordinated and frozen and still wait months for sanction, or be forced to change late because the authority requires a lower height or a wider setback. That is why the design stages and the approvals track must be planned together from the start: you begin the sanction process as early as the design is stable enough to submit, you design with the development-control rules in front of you rather than discovering them late, and you build float into the programme for the authority's response and for likely revisions.

The architect's role here is to explain the principles to the client and to steer the process, while deferring specifics to the local authority and the current regulations - the exact rules, formats and timelines vary by city and change over time, so verify at source rather than assume. A design that ignores the approvals track until documentation is a design that will be redrawn under pressure at the worst possible moment.

Two tracks, two clocksDESIGN TRACKConceptDeveloped designDetailed designDocsAPPROVALS TRACKSanction drawingsFire / environmentUtility NOCs / occupancysubmit when stablelate approval change hits documentationPlan the two tracks together - the authority will not wait for your design.
Zoom
The design track and the statutory-approvals track run on parallel clocks. Sanction drawings and clearances start once the scheme is stable and proceed on the authority's timescale, so they must be planned alongside the design and can force a change if ignored until documentation.
Keeping control

Coordination, records and the design freeze

Across all the design stages, two disciplines separate a controlled project from a chaotic one. The first is coordination management: someone - usually the architect as lead consultant - must actively drive the exchange of information between the design team, chase the engineers for their inputs, run coordination reviews, and resolve clashes deliberately rather than hoping they resolve themselves. On anything beyond a small house this is a genuine management task, and it is why Modules 6 and 7 treat coordination and the project team at length.

The second is record discipline. Every stage should end with a clearly issued, dated, version-controlled set of deliverables and a recorded client sign-off, so the project always has an unambiguous current baseline. Sloppy version control - three people working on three different plans - is one of the most common and most expensive failures in practice, producing buildings where the electrical layout was coordinated against a superseded architectural plan. A simple, rigorously kept drawing register and issue sheet prevents an astonishing amount of grief.

Above all, protect the design freeze. The design stages exist to move the project from open questions to settled decisions, and the value of that settling evaporates if the client, or the architect's own restlessness, keeps reopening decisions after they are made. Change is legitimate and sometimes necessary - but after the developed-design freeze it must be handled as a conscious, costed, approved variation, not an informal tweak. The practice that holds the freeze delivers on time and on budget; the one that lets the design drift redraws forever and blames everyone but itself.

Version control is cheap; a building coordinated against the wrong plan is not.

Bodies, documents and frameworks

RIBA Plan of Work 2020 - Stages 2, 3 and 4

Concept Design, Spatial Coordination (Developed Design) and Technical Design, with defined objectives and information exchanges for each

A clear reference for what each design stage should resolve and deliver; adapt the level of detail to the project.

AIA phases - Schematic Design and Design Development

The North American definition of the early and developed design phases and their deliverables

A compatible dialect; useful for describing the escalating resolution of drawings and the coordination expected at each phase.

Development-control and building rules (local authority) / NBC via BIS

The statutory requirements a sanction submission must satisfy - coverage, floor-area ratio, setbacks, heights, parking, fire and life-safety provisions

Design with these in front of you and run the approvals track in parallel; verify the exact rules, formats and status with the local authority and the current regulations rather than assuming.

Design coordination and the design freeze

The management discipline of coordinating architecture, structure and services and of locking the design at the end of developed design

Coordination is an active management task and the freeze is what protects programme and budget; changes after it are costed variations.

Hands-on workshop

Workshop - map the deliverables and coordination for each design stage

This exercise builds a stage-by-stage deliverables and coordination matrix for a real project, so you can see exactly what is produced, by whom, and what is being approved at each gate. About an hour with a spreadsheet.

A spreadsheet, the RIBA Plan of Work as a deliverables reference, and the local development-control rules.

Given & goal
Goal: a deliverables-and-coordination matrix across concept, developed and detailed design
Inputs: a real or imagined project and its likely consultants
Time: ~60 minutes
  1. 1For each of the three design stages (concept, developed, detailed), list the specific architectural deliverables - name the drawings, their scale, and any narrative, model or specification that accompanies them.
  2. 2For each stage, note what each consultant (structural, MEP, cost, others) must contribute, and what has to be exchanged and coordinated before the stage can close. Identify the likely clash points - where structure or services threaten the architecture.
  3. 3Mark the client sign-off at each gate: state in one sentence what the client is approving and what proceeding authorises. Note how you will record that approval.
  4. 4Draw the statutory-approvals track alongside: when the sanction and other clearance submissions are prepared and lodged relative to the design stages, and where they could force a change.
  5. 5Identify your design-freeze point and write the one-line rule your team will follow for any change requested after it (evaluate ripple, cost it, get it approved as a variation).

You’ll walk away with
A one-page matrix showing, for concept, developed and detailed design: the architectural deliverables, the consultant coordination, the client sign-off, and the parallel approvals - with a stated design-freeze point and change rule.

The worked example

Three altitudes on the same idea

Read the band that fits you — or all three.

For the architectRun projects and a practice with command

As principal, own the resolution sequence: insist the concept is genuinely signed off before developed design, drive the design freeze at the end of developed design, and treat everything after as a costed variation. Make coordination an explicit management activity, not an afterthought, and keep rigorous issue and version control so the whole team always works to one baseline. Plan the statutory-approvals track from day one, because it will not wait for your design to be ready.

For the project leadDeliver on time, on budget, on brief

As the project lead, you run the design programme: track what each stage must deliver, whose input you are waiting for, and when the client sign-off is due, and chase the consultants so coordination actually happens on time. Guard the design freeze fiercely - the moment a 'small change' arrives after developed design, evaluate its ripple through structure, services and cost and handle it as a formal variation. Keep the drawing register clean so nobody ever builds against a superseded plan, and run the approvals track as a parallel programme with its own milestones.

For the studentThe business of architecture, made clear

Understand that design resolves from coarse to fine: the big move first, then the arrangement, then the systems, then the junctions - and that each is settled and coordinated before the next is refined. In your own studio work, resist detailing a wall before your plan and section are resolved; you will save yourself endless redrawing. Learn to read a section as the place where architecture, structure and services must all be reconciled, and practise producing clear, economical concept drawings that communicate an idea rather than over-rendered images that hide unresolved thinking.

Misconception check

Once the client loves the concept, the rest of the design stages are just drafting - turning the pretty pictures into technical drawings. The real creative work is over.

The concept is only the first and coarsest of the design decisions, and far from the whole job. Developed design is where the idea is tested against reality - fixed in dimension, given a structure, coordinated with services so the ducts fit above the ceiling and the columns miss the rooms - and it routinely forces the concept to adapt. Detailed design is where a building's quality and durability are actually decided, in the junctions and details that keep water out and finishes meeting cleanly; a beloved concept with an unresolved parapet still leaks. And through all of it the architect is coordinating a team of consultants and steering the statutory approvals that can force the scheme to change. Treating everything after the concept as mere drafting is exactly how practices produce schemes that fall apart in coordination, blow the budget in detail, or get redrawn under pressure to satisfy an authority. The creative and judgement-heavy work continues, in a different register, right up to the moment the design is fully documented.
Try it

Do it yourself

Sharpen your grip on the design stages with these.

  1. 1Name the deliverables at the end of concept versus the end of developed design for a small building. Why are the scales and level of resolution different?
  2. 2Give a concrete example of a services-versus-architecture clash that developed design should catch on paper, and what it costs if it is missed until site.
  3. 3Why is the end of developed design the right place to freeze the design? What changes become expensive after it?
  4. 4How would you plan the sanction submission so the approvals track does not force a late redesign?
Take this with you

The one line to carry out

The design stages carry a project from a coarse concept, through a coordinated developed design that is tested against structure, services and budget and then frozen, to a detailed design that resolves every junction so the building can be documented and built - all while the architect coordinates the consultant team, secures an explicit client sign-off at each gate, keeps rigorous version control, and runs the statutory-approvals track in parallel on its own clock.
Take it further
References & further reading

Peer-reviewed journals & authoritative standards

  1. 01RIBA Plan of Work 2020 Overview (Stages 2 to 4)Royal Institute of British Architects (RIBA), 2020.
  2. 02The Architect's Handbook of Professional Practice, 15th edition (AIA)The American Institute of Architects / Wiley, 2013.
  3. 03National Building Code of India and design compliance (IS codes)Bureau of Indian Standards (BIS), 2024.
  4. 04Design development and coordination in the construction processDesigning Buildings Wiki, 2024.
Related lessons
Recap
Design resolves from coarse to fine. Concept fixes the big move and wins the crucial client sign-off; developed design fixes dimensions, structure, materials and systems, coordinates the consultants, checks cost, and freezes the design; detailed design resolves the junctions and specialist elements so nothing significant is left open. Deliverables escalate in resolution stage by stage, each gate closes with a recorded client approval, and the statutory-approvals track runs in parallel, able to force change if ignored. Coordination is an active management task and version control protects the single baseline.
Carry forward →

With the design fully resolved and frozen, the project must now be turned into the complete package of drawings, schedules and specifications from which contractors can price and build it - the documentation and tender stage, where design becomes buildable instruction.

A

The author

Amogh N P

Architect, interior designer, and creative polymath. Studio Matrx began in his notebooks — his vision of design made honest, useful, and open to everyone. Its Academy is written and taught in his memory, and free, forever.

More about Amogh →