Pre-Work Audit

Pre-Renovation Prep Checklist

Settle everything before hammers come out. 10 categories, 65+ checkpoints — society, neighbours, utilities, contract, protection, debris, stay / move-out, safety, schedule, insurance.

0

Pass

0

Fail

0

N/A

55

Pending

0%

Ready

Project Details

🏢

Society / Association Approvals

Written NOC from society

Application submitted with scope of work

Managing committee approval letter

Date range of work stated

Security deposit paid (if required)

Structural work clearance

No demolition of RCC walls without structural engineer sign-off

Architect's plan approved by society engineer if required

No additions to facade without permission

Work-hour restrictions

Permitted hours confirmed (usually 9 AM – 6 PM)

Silence zones around exam / festival periods

No Sunday / holiday work (in most societies)

Workers access

Worker ID / police verification if required

Service lift usage rules

Visitor pass / gate entry process

Debris management clause

Daily debris removal rule

No accumulation in common areas

Dumping location and fees

Deposits and charges

Security deposit to cover damage

Lift / common area damage clause

Fines for rule violation

👋

Neighbour Intimation

Direct neighbours informed

Flats adjacent (left / right / above / below)

Written / WhatsApp intimation with dates

Contact number shared for concerns

Detailed scope shared

Nature of work (plumbing / structural / painting)

Noise-intensive phases identified

Wet work days flagged

Pets and elderly

Adjacent flats with pets / elderly informed separately

Options to reduce impact discussed

Wall-shared work

Drilling on common walls intimated

Window timings agreed (morning preferred)

Dispute escalation path

Society committee copy on intimation

Logs kept of any complaint received

⚙️

Utilities & Temporary Setup

Water connection for workers

Source identified (tap / temporary line)

Water bill reading recorded before work

Metered vs unmetered charges clarified

Electrical connection

Worker power from dedicated circuit

ELCB on site

No tapping from neighbour

Meter reading recorded before work

Temporary toilet / wash

Identified location for workers

Agreement with society

Hygiene maintained

Waste segregation

Bins for dry / wet / construction debris

No mixing with society bins

Vendor booked for C&D removal

Gas / internet isolation

Gas meter location protected

Wi-Fi router moved to safe zone

ISP informed if service expected to be interrupted

📝

Contract & Scope Lock

Detailed BOQ signed

Every line item priced

Brands and specifications locked

No 'as agreed verbally' items

Payment milestones

Tied to completion percentage

No large advance (< 20%)

Retention 5-10% until final snag clearance

Timeline and penalties

Start and end dates signed

Daily / weekly penalty for delay

Force majeure clause

Scope freeze

Variation order process written

Price changes only with signed variation

No verbal extras

Warranty

Workmanship warranty minimum 1 year

Waterproofing 5 years

Material warranties pass-through from brand

Payment method

Bank transfer with invoice

GST invoice for input tax credit

No large cash payments

Termination clause

Exit terms if contractor defaults

Material and tool ownership clause

Partial payment settlement formula

🛡️

Home Protection & Preparation

Floor protection

Corrugated boards / tarpaulin on existing flooring

Extra protection at door thresholds

No direct trolley movement on tiles

Furniture storage

Items moved to one locked room

Covered with plastic sheet

Inventory list made

Valuables off-site

Kitchen and bath isolation

Unrelated fixtures covered

Taps protected

Appliances disconnected and stored

Electronics and soft furnishings

TV, PC, speakers packed and stored off-site if possible

Curtains / rugs removed

Books / art stored

Plants and pets

Plants moved to balcony or neighbour

Pets relocated or kept in one sealed room

Boarding booked for noise-intensive phases

Walls and doors

Non-work doors taped and kept shut

Switchboards covered

Door hinges greased before work to ease shut-close

🚛

Debris & Material Management

Debris removal vendor

C&D waste vendor engaged (licensed)

Pickup schedule set

Cost per trip / tonne agreed

On-site staging area

Designated area within flat or society

No blocking of common pathways

Protected from rain (tarpaulin)

Material delivery schedule

Heavy / bulk material in off-peak hours

Coordinated with society security

No flat / lift blocking

Dust control

Plastic sheeting at doorway

Wet sweeping (not dry)

Air quality managed for asthma / senior neighbours

Hazardous material handling

Asbestos identified (old buildings) — special disposal

Lead paint check in pre-2000 homes

Chemical containers stored safely

📦

Move-Out / Stay-Through Planning

Decision — move out or stay

Full move out for full home renovation

Partial / room-by-room if staying

Short-term rental / hotel budgeted

Temporary residence logistics

Location and duration set

Essential items packed (medicines, documents, clothes)

Address update for deliveries

Essentials kept accessible

Medicines, passport, work documents

Chargers, laptops

Change of clothes

Meal plan during work

Kitchen access planning

Tiffin service / eating out budget

Gas cylinder refill before start

Kids and school routine

School pickup / drop adjusted

Study space maintained

Noise impact on study hours planned

⚠️

Safety During Work

Worker safety gear

Helmets at demolition stage

Goggles / masks for cutting / grinding

Gloves for handling sharp materials

Contractor responsibility in writing

First-aid on site

Kit accessible on site

Nearest hospital identified

Accident insurance for workers (contractor responsibility)

Fire safety

Extinguisher on site during hot work (welding / torch)

No smoking zones

Flammable materials stored separately

Electrical safety during work

Licensed electrician for any alterations

No exposed wiring

ELCB at power take-off

Temporary lighting IP rated

Children and pet safety

Locked doors to work area

No access during active work

Communication with workers on timing

Neighbour safety

Scaffolding safe for passers-by below

Falling-object protection

Warning signage

📅

Schedule & Communication

Weekly schedule shared

By contractor — what happens this week

Milestones marked

Any slippage flagged on Monday

Site visit schedule

You or your representative visits fixed days

Record of each visit

Sign-off after each milestone

Daily site log

Workers on site

Material received

Work completed

Issues raised

Design decision dates

Calendar of 'decide by' dates for materials, colours, hardware

No decisions held as blockers

WhatsApp / project group

Group with you, contractor, designer

Photo updates daily

Written record of instructions

📋

Insurance & Documentation

Home insurance update

Insurer informed of renovation

Cover during work period confirmed

Renovation exclusions reviewed

Contractor insurance

Workmen compensation valid

Third-party liability cover

Copy of policy on record

Before-work photos

Every room photographed

Existing damage / condition dated

Shared to all stakeholders

Legal documents safe

Title, sale deed, society papers off-site

Digital scans cloud-backed

GST and vendor compliance

Vendor GSTIN verified

Input tax credit eligibility clarified

Bills / invoices filed weekly

Download Pre-Renovation PDF

Complete every item before day one. Most renovation disputes start here, before any physical work begins.