Pre-Possession Inspection Checklist
Inspect your flat before you register it. 10 categories, 70+ checkpoints — legal documents, carpet area, structure, finishes, and deviations from the sale agreement.
0
Pass
0
Fail
0
N/A
61
Pending
0%
Inspected
Inspection Details
Legal & Documents
Occupancy Certificate (OC)
Original OC issued by municipal authority
Building name, flat number match
Not partial / conditional OC
Date of OC noted — don't register without this
Completion Certificate (CC)
Original CC received
Matches approved plan
Any deviation flagged in CC?
Khata / Mutation
Khata certificate / mutation entry in your name or builder's name
Khata extract provided
Property tax paid up to date — check receipt
Encumbrance Certificate
Latest EC for the land + flat
No pending mortgage beyond what you're settling
30-year EC for resale; 13-year minimum for new
Approved building plan
Sanctioned plan copy received
Matches what's built on ground
Revised/modified plans on record if any deviation
Sale deed / registration papers
Draft sale deed reviewed by lawyer
Carpet area declared on papers matches actual (RERA)
Common area share defined
Stamp duty and registration fee calculated
RERA registration
Project RERA number displayed on site
RERA carpet area matches sale agreement
Quarterly progress reports on RERA portal
Society formation
Apartment association formed or formation date given
Bye-laws draft shared
Corpus fund amount disclosed
Maintenance charges structure provided
Carpet Area Verification
Carpet area (RERA definition)
Measured wall-to-wall excluding external walls
Excludes balcony, terrace, shaft
Within ±3% of sale agreement
Discrepancy greater than 3% is refundable under RERA
Balcony area
Separately measured
Matches plan
Open to sky (not enclosed)
Railing height ≥ 1000mm (NBC)
Utility area
Separately measured and disclosed
Usable for washing machine + drying
Super built-up vs carpet
Loading factor disclosed (usually 1.3–1.5)
You are paying per carpet area (RERA requirement post-2017)
Ceiling height
Minimum 2.75m clear (NBC)
Consistent across rooms
No unexpected drops from false beams
Structural & Walls
No visible structural cracks
No diagonal cracks at beam-column junctions
No cracks wider than 1mm
No cracks through RCC members
Wall plaster
No hollow sounds (tap test)
No visible cracks
Even finish — no undulations
Plumb — no lean
Beams and columns
No exposed reinforcement
No honeycomb in concrete
Beams level — no sagging
Columns plumb
Slab condition
No water seepage marks on ceiling
No efflorescence (white powdery deposits)
Slab thickness matches specification
Dampness check
Run moisture meter on all external walls
No damp patches visible
Corners and skirting areas dry
Waterproofing & Leakage
Bathroom waterproofing
Ask for flood-test certificate (48-hour ponding)
No damp marks on ceiling below bathroom
Threshold hump present
Slope toward drain correct
Terrace waterproofing
If top floor — check ceiling for stains
Terrace accessible for inspection
Visible waterproofing layer (not just plaster)
Proper slope toward drain holes
Kitchen dry area
No dampness around sink area
No staining on adjacent walls
Utility / washing area
Properly waterproofed
Drain functional
No wall damage from past leaks
External wall leakage
No seepage marks from outside
Monsoon trial if possible
Window frame junction sealed
Parapet and coping
Coping covers parapet top
No gaps at joints
Drip moulding present on balcony edge
Plumbing
Water supply pressure
Adequate pressure on top floor
Both overhead and underground tank supply working
No air locks in lines
All taps functional
Every tap in every bathroom + kitchen + utility runs
Hot water from geyser (where fitted)
No drips when closed
Drain test
Pour 10 litres in each floor trap — drains within 2 min
Kitchen sink drains quickly
WC flushes fully
No gurgling / sewer smell
WC and fixtures
Firmly bolted
Concealed cisterns don't leak
Silicone seal at floor junction
Seat covers intact
Water tank capacity
Allocated share per flat documented
Overhead + underground capacity disclosed
Booster pump operational (if provided)
Hot water lines
Separate hot water lines where geysers are fitted
Insulation on hot water pipes
No cross-connection with cold water
Pipe material disclosure
CPVC / PPR for water supply — confirmed
SWR for drainage — confirmed
Brand/make matches agreement
Electrical
Sanctioned load
Matches what was promised
Certificate from electrical authority
Sufficient for your planned AC / geyser load
All switches work
Test every switch against mapped light/fan point
No loose fittings
No reverse polarity (use tester)
MCB / RCCB panel
RCCB present for each sub-circuit
Trips when test button pressed
Clear labelling of circuits
Brand matches specification
Earthing
Earthing resistance < 1 ohm (ask for test certificate)
All metal fixtures earthed
Geyser earthed
AC and geyser points
15A points at bedroom AC locations
15A point at bathroom for geyser
Adequate point count per room
Power back-up
DG backup points clearly marked on switchboard
Backup load allocated per flat disclosed
Inverter-ready wiring if promised
TV / cable / internet points
In every bedroom and living room
Working — confirm with cable vendor
Structured cabling disclosed
Finishes & Fixtures (vs Agreement)
Flooring
Material matches agreement (vitrified/marble/wood)
Brand matches where specified
No chipped / cracked tiles
No hollow tiles (tap test)
Consistent pattern and shade
Doors
Main door — solid wood as promised
Internal doors — material matches
Door hardware brand matches
No warping, peeling, scratches
Windows
Material matches (UPVC / aluminium / wood)
Brand confirmed (Fenesta / LG / Lingel, etc.)
Mosquito mesh where promised
Open-close-lock all functional
Kitchen platform
Granite / quartz / other as per agreement
Sink material as promised
Overhang sufficient (20-40mm)
Bathroom fittings
CP fittings brand matches (Jaquar/Grohe/Kohler)
Sanitary ware brand matches (Hindware/Cera/Kohler)
Anti-skid tiles in wet areas
Tiles up to ceiling height as promised
Paint
Brand and type match (Asian/Berger/Nerolac)
Interior emulsion as promised
External weatherproof paint on external walls
Even finish, no patches
False ceiling
Only where promised
Material matches (gypsum / POP)
Even finish, no sagging
Common Areas & Amenities
Lifts
All promised lifts installed and operational
Capacity matches agreement
Stretcher lift for buildings > 4 floors (NBC)
Licence + inspection certificate
Fire safety
Fire NOC issued
Hydrants, sprinklers, alarms per plan
Emergency staircase accessible
Fire extinguishers installed
Clubhouse / gym / pool
All promised amenities complete
Operational (not 'coming soon')
Fixtures match brochure
Landscaping
Completed as per plan
No pending civil work
Borewell / STP / WTP
Sewage treatment plant operational
Water treatment plant operational
Borewell yield disclosed
Solar / rainwater harvesting
Installed where mandated by city bylaw
Certificate provided
Capacity matches specification
Security
CCTV coverage at entry, lift lobbies, parking
Intercom to each flat functional
Gate and boundary wall complete
Parking & Storage
Parking allocation
Parking number mentioned on sale deed (not just allotment letter)
Covered vs open parking clear
Size adequate for your car
Column positions don't block door swing
EV charging
EV-ready point provided if promised
Load allocated for EV charging
MCB from your flat's meter (not common)
Storage / scooter parking
Scooter parking as per brochure
Storage room / mezzanine as promised
Visitor parking
Number of slots disclosed
Not double-allocated to flat owners
Deviations & Snag List
Plan vs as-built
Walk through with sanctioned plan in hand
Any extra wall / reduced room size documented
Any common-area encroachment flagged
Brochure vs reality
All promised amenities present
Features not quietly removed (e.g., marble → vitrified)
Size of rooms not shrunk
Snag list signed
All snags documented in writing
Timeline for rectification set (usually 30-60 days)
Retention from builder payment until cleared
Handover letter
Take physical handover only after satisfying inspection
Inventory of keys, remotes, documents signed
Utility meter readings recorded (water, electricity, gas)
Defect liability period
DLP clause in agreement (5 years under RERA)
Structural defect coverage confirmed
Contact for rectification given
Download Pre-Possession Report PDF
Share with your lawyer, builder, or family before you register. Demand written response on every Fail before paying final instalment.
Related Tools — You may also find these useful
Snag Checklist
Professional interior snag checklist for handover inspection across 10 work categories.
Snag ListSite Inspection Checklist
57-point checklist across 8 work areas for every site visit and stage-gate inspection.
Execution ChecklistElectrical Safety & Load Audit
Home electrical audit — 10 categories, 65+ checkpoints across earthing, RCCB, MCB, wiring, switchboards, appliance circuits, DG/inverter backup.
Safety Audit