Studio Matrx Monthly · Volume 1 · Issue 2 · July 2026
Amogh N P
 In loving memory of Amogh N P — Architect · Designer · Visionary 
Bathroom Fixture Schedule (India): A Tagged Sanitaryware & CP Fitting Schedule for Procurement
Bathrooms

Bathroom Fixture Schedule (India): A Tagged Sanitaryware & CP Fitting Schedule for Procurement

A copy-and-use fixture schedule for Indian bathrooms — every WC, basin, mixer, health faucet, shower set and accessory tagged (WC-1, BS-1, FT-1), specced and finish-coded, so procurement, plumbing and site coordination all read from one sheet.

9 min readAmogh N P12 July 2026Last verified July 2026
A neatly organised sanitaryware and CP fitting layout on a site table with tag labels, alongside a printed fixture schedule sheet

A fixture schedule is the single sheet that stops a bathroom project from turning into a series of arguments. It lists every piece of sanitaryware and every chrome-plated (CP) fitting once, gives each a tag, pins down the model and finish, and tells procurement how many to buy and where each one goes. When the WC on the drawing, the WC in the BOQ, the WC in the purchase order and the WC that lands on site are all "WC-1", nobody guesses, nobody substitutes silently, and nobody pays twice.

This is a working document, not an essay. Copy the tables below into your own project sheet, swap the example rows for your specification, and issue it alongside the tile layout and the bathroom plumbing schedule. It sits between design freeze and procurement, and it stays live — updated — right through to handover.

One golden rule: a fixture is only "decided" when it has a tag, a model number and an approved finish. Anything specified as just "good quality wall-hung WC" will be value-engineered into whatever the plumber's dealer had in stock.

How to use this document

  • Who fills it in: the architect or interior designer specifies; the site engineer or PMC tracks status; the contractor procures against it.
  • When it is issued: at design freeze, before the first sanitaryware purchase order. Re-issue on every revision (mark Rev 1, Rev 2 with a date).
  • How to read a tag: two letters for the family, a number for the variant. WC-1 and WC-2 are two different water closets in the same project; the number is not a quantity.
  • Golden source: the schedule references the drawings, not the other way round. If a mixer moves on the elevation, the schedule row is what gets corrected and re-circulated.
  • One project, one legend: publish the tag legend on the first sheet so every trade uses WC-1 to mean the same pan.

The tag convention

Keep it short and readable. A common India-friendly set:

  • WC — water closet (pan) · CT — cistern / flush plate · BS — basin · CP counter/vanity basins can share BS with a sub-note
  • FT — CP fitting (basin mixer, bib cock, angle valve) · HF — health faucet · SH — shower set (mixer + head) · DV — diverter
  • GY — geyser / water heater · FD — floor drain / trap · AC — accessory (towel rail, robe hook, paper holder, grab bar)

The fixture schedule

This is the deliverable. Every row is one tagged item. Rates are indicative ex-showroom ranges (2026) and vary by city, brand tier and finish — never treat them as a quote. Fill the Qty and Location columns per your actual layout.

TagItemType & specFinishQtyLocationRemarks
WC-1Water closetWall-hung rimless pan, P-trap, 180 mm projection from finished wallVitreous white3Master, Common, GuestOn concealed cistern; seat with soft-close cover
WC-2Water closetFloor-mounted one-piece, S-trap 220 mm set-outVitreous white1Powder roomVerify trap distance on plumbing schedule
CT-1Concealed cistern + plate2-inline frame cistern, dual flush 3/6 L, rectangular plateMatt chrome plate3With WC-1Confirm wall thickness ≥ 115 mm for frame
BS-1Wash basinUnder-counter basin 500 x 400 mm, single tap holeVitreous white3On vanity countersCut-out template from vendor before stone cutting
BS-2Wash basinTable-top (vessel) basin, 400 mm roundMatt white1Powder roomNeeds tall/extended-body mixer FT-2
FT-1Basin mixerSingle-lever pillar mixer, 35 mm cartridge, incl. pop-up wasteChrome (CP)3With BS-1Supply with 2 angle valves + connection pipes
FT-2Basin mixerTall-body single-lever mixer for vessel basinMatt black (PVD)1With BS-2Confirm spout height clears basin rim
FT-3Angle valveQuarter-turn angle stop cock 15 mm, ceramic discChrome (CP)14All basins/WC/HF feedsOrder surplus; count = all fixture stop cocks
HF-1Health faucetABS spray gun, 1 m flexible tube + wall hook, with stop cockChrome / white gun4Beside every WCOne per WC + powder room
SH-1Shower setConcealed diverter mixer + overhead rain shower 200 mm + hand shower on railChrome (CP)2Master, Common bathRough-in body ordered with plumbing 1st fix
SH-2Shower setSingle-lever concealed mixer + overhead 150 mmChrome (CP)1Guest bathNo hand shower; confirm with client
DV-1Diverter3-way concealed diverter (overhead / hand / spout)Chrome (CP)2With SH-1Match brand to SH-1 for trim compatibility
GY-1Water heaterStorage geyser 15 L, 2 kW, 5-star, ISI markedWhite body4Above each shower zoneWall bracket + safety valve; see electrical scope
FD-1Floor drainAnti-cockroach floor trap 100 x 100 mm, high-flow gratingMatt CP / SS 3046Shower + WC zonesGrating to match tile module; deep-seal type
AC-1Towel rail600 mm single towel rod, concealed fixingChrome (CP)4All bathsFix into hard blocking, not tile alone
AC-2Robe hookSingle/double robe hookChrome (CP)6Behind doors
AC-3Paper holderRecessed / surface toilet paper holder with flapChrome (CP)4Beside each WCSet-out 200 mm from WC front, 750 mm AFF
AC-4Grab bar600 mm SS 304 grab bar, 32 mm dia, load-ratedMatt SS / anti-slip2Elder + accessible bathFix to studs/blocking; see accessible design guide

Add a totals row per family at the bottom of your working copy so the purchase order quantities fall straight out of the schedule.

Where the schedule lives in the project 1. Design freeze Specify + tag every fixture 2. Procurement PO by tag + approved finish 3. Rough-in Concealed bodies set per set-out 4. Install Trims fixed, status closed The same tag carries through every stage — drawing, BOQ, PO, delivery note and snag list.

Finishes & colour reference

Half the site disputes on fittings are about finish, not fixture. Lock the finish codes here, and quote the code (not "silver-ish") on every purchase order. PVD finishes cost more but resist scratching and hard-water spotting far better than electroplated chrome — worth it in matt black and gold, which show wear fastest.

Finish codeDescriptionTypical useCare note
CPPolished chrome (electroplated)Default for FT, SH, ACWipe dry; avoid acidic descalers on the plating
MBMatt black (PVD)Feature mixers, powder roomShow water spots in hard-water cities — dry after use
BGBrushed gold / rose gold (PVD)Premium / accent bathsPVD only; electroplated gold flakes
BNBrushed nickel (PVD)Warm, low-glare schemesHides limescale better than CP
SSStainless steel 304Grab bars, gratingsStructural + hygienic; magnet-test grade on delivery
WHVitreous / matt whiteSanitaryware, geyser bodyMatch white tone across brands — sample first

Do not mix finishes by accident. If the scheme is CP, a single matt-black angle valve that slipped through on a substitution will be the first thing a client notices. Approve one finish per zone in writing.

Coordination & approval status

This is the tracker that keeps everyone honest. Run it as a live column set beside the schedule: a fixture moves left-to-right from Specified → Approved → Ordered → Delivered → Installed, and nothing gets fixed on site until "Approved". Update it weekly and colour the laggards.

TagSpecifiedApprovedOrderedDeliveredInstalledOwnerNotes
WC-1YesYes (12 Jun)PO-014YesPending trimContractorAwaiting flush plate CT-1
CT-1YesYesPO-014PendingContractorFrame installed at 1st fix; plate later
BS-1YesYes (12 Jun)PO-015YesYesContractorStone cut-out verified
FT-2YesPendingDesignerClient to confirm matt black vs CP
SH-1YesYesPO-016Body onlyRough-in donePMCTrim kit due before tiling handover
GY-1YesYesPO-018Yes2 of 4ElectricalCoordinate with DB + point location
AC-4YesPendingDesignerConfirm blocking with civil before order

Keep the PO number in the "Ordered" cell — it links the schedule to the paper trail so any delivery can be traced back to one line.

The approval gate Specified tag + model Approved finish signed Ordered PO raised Delivered checked vs spec Installed status closed Gate: no fixing before Approved Unapproved trims fixed to tile = breakage on rework. Verify finish and hand before the wall.

Common mistakes

  • Quantities read as variants. WC-2 does not mean "two WCs" — it is the second type. Keep quantity strictly in the Qty column.
  • No concealed-body rough-in coordination. Concealed cisterns, diverters and shower mixers must be ordered before first-fix plumbing. Order the trim late, but never the body.
  • Set-out distances missing. A P-trap pan (180 mm) on an S-trap set-out (220 mm) will not sit flush. Cross-check every WC and basin against the plumbing set-out before ordering.
  • Finish specified in words, not codes. "Rose gold" from two brands rarely matches. Reference the finish code and approve a physical sample.
  • Blocking forgotten. Towel rails, grab bars and wall-hung WCs pulling out of tile is the classic snag. Confirm blocking or a frame under every wall-mounted item before it is ordered.
  • Schedule not re-issued after revision. An out-of-date schedule is worse than none — mark every revision with number and date, and withdraw the old one.

Treat this schedule as a starting point, not a final specification. Verify every tag, set-out and quantity against your actual drawings, the signed contract and current IS codes, and have a licensed plumber and your PMC confirm before you raise a purchase order.

Related resources & guides

Export this guide