Studio Matrx Monthly · Volume 1 · Issue 2 · July 2026
Amogh N P
 In loving memory of Amogh N P — Architect · Designer · Visionary 
Security BOQ Template for India (2026): Pricing the System Line by Line
Security

Security BOQ Template for India (2026): Pricing the System Line by Line

A ready-to-adapt security Bill of Quantities: the priced, itemised list of everything to be supplied and installed, used to tender the job, hold bidders to a like-for-like comparison and set the contract sum — with a worked example and a blank copy-ready template.

12 min readAmogh N P26 July 2026Last verified July 2026
A consultant and contractor at a table reviewing a priced security Bill of Quantities with the equipment schedule and specification open alongside

A security boq template is the priced, itemised backbone of the procurement stage — the Bill of Quantities that lists every item to be supplied and installed, so that a security system can be tendered, compared and awarded on a like-for-like basis. It is not the design and it is not the specification. It is the counting-and-pricing document: one line per item, a quantity, a unit, and two empty rate columns the bidder fills in. Add the rates up and you have the contract sum.

The BOQ is built downstream of the equipment and device schedule (which fixes what and how many) and the specification (which fixes the required quality and standard). It is then issued inside the tender pack for bidders to price. Because every bidder receives the identical BOQ, their totals can be compared row by row — that comparability is the whole point.

Scope & how to read this. This is a ready-to-adapt professional template, not authoritative, contractual or legal wording. The BOQ becomes part of a commercial contract, so get proper commercial, procurement and legal review before you issue or award. Quantities come from your project and your schedules; rates come from the bidder; taxes follow your commercial terms. Do not copy this page into a live tender unchanged.

A flow diagram showing the equipment schedule and specification feeding into the BOQ, which is issued in the tender, priced by bidders, compared like-for-like and becomes the contract sum

Where the BOQ sits in procurement

Read left to right across the project. The schedule answers "what and how many." The specification answers "to what quality and standard." The BOQ turns those into a priceable list. The tender wraps the BOQ in the commercial and legal terms and issues it. Bidders return the BOQ with rates entered; you total and compare; the winning priced BOQ becomes the contract sum and the yardstick for measuring the work as it is built and for valuing any change.

That lineage matters because it tells you what belongs in the BOQ and what does not. Descriptions in the BOQ point back to the spec rather than repeating it. Quantities trace to the schedule and must match it exactly. Rates are the one thing the BOQ leaves blank — they are the bidder's commercial offer, and you never fill them in for them.

The columns

A workable security BOQ is a table with a small, disciplined set of columns. Keep them stable across every subsystem so the sheet reads the same all the way down.

ColumnWhat it holdsNotes
Item no.A stable code, e.g. 1.02Keys the line to the tender and the spec clause
DescriptionThe item in plain wordsTied to the spec; enough to price, not a re-write of the spec
Make / modelA named make, or "as specified"Use "as specified" when the spec fixes the standard
UnitNo., m, set, lotThe unit the rate is quoted against
QuantityThe count or lengthMust match the equipment schedule
Supply ratePrice to supply one unitBlank in your issued BOQ; bidder quotes
Install ratePrice to install one unitKept separate from supply, never merged
AmountQty x (Supply + Install)Computed by the bidder
RemarksProvisional sum, exclusions, notesWhere you flag anything unusual

Beyond the equipment lines, a complete BOQ carries a few item groups that are easy to forget and expensive to omit:

  • Preliminaries / general items — site establishment, supervision, safety, as-built documentation, warranties and training. Real cost that hides if you leave it out.
  • Cabling and containment — cable by type and length, conduit, trunking, trays and glands, as their own measured items rather than buried inside each device.
  • Testing and commissioning — a distinct line for proving the system, not an assumed freebie.
  • Spares and AMC — a spares holding and an annual maintenance line (or a provisional sum) so support is priced up front, not negotiated later.

A column map of the security BOQ showing item number, description, make, unit, quantity, supply rate, install rate and amount, with the rate cells marked quote and separate notes on supply-versus-install and the extra item groups

Worked example BOQ (illustrative)

Below is a short, illustrative BOQ grouped by subsystem to show the shape. Note that every rate is left as "quote" — in a real issued BOQ these cells are blank for the bidder to price. The descriptions, makes, quantities and figures here are generic placeholders to show format only.

Example only — adapt to your project. Values below are illustrative. Do not treat any quantity, make or grouping as a recommendation; derive yours from your own schedule, spec and site.

ItemDescriptionMake / modelUnitQtySupplyInstallAmount
1Preliminaries and general items
1.01Site establishment, supervision and safetyas specifiedLot1quotequotequote
1.02As-built drawings, O and M manuals, warrantiesas specifiedLot1quotequotequote
2CCTV subsystem
2.01Fixed dome camera, e.g. 4MP, as specas specifiedNo.12quotequotequote
2.02Bullet camera, e.g. 4MP, as specas specifiedNo.6quotequotequote
2.03Network video recorder, channels as specas specifiedNo.1quotequotequote
2.04Storage drive, capacity as specas specifiedNo.2quotequotequote
3Access control
3.01Controller, doors as specas specifiedNo.1quotequotequote
3.02Reader at entry, type as specas specifiedNo.4quotequotequote
4Cabling and containment
4.01Data cable, category as specas specifiedm900quotequotequote
4.02Conduit / trunking, size as specas specifiedm600quotequotequote
5Testing, commissioning and support
5.01Testing and commissioning of full systemas specifiedLot1quotequotequote
5.02Recommended spares holdingas specifiedSet1quotequotequote
5.03Annual maintenance (AMC), first yearas specifiedYear1quotequotequote
Sub-total (ex taxes)quote
Taxes (GST) per commercial termsquote
Totalquote

Two things to read from that table. First, supply and install stay in separate columns for every device — that lets you sanity-check a bid where the supply looks cheap but the install is padded, or vice versa. Second, the sub-total, taxes and total sit at the foot; GST is handled per your commercial terms, not baked into each rate, so the comparison stays clean.

Blank copy-ready template

Copy this into your sheet, keep the columns, and replace the placeholder rows. Group your own subsystems the same way (preliminaries, each subsystem, cabling and containment, testing and commissioning, spares and AMC). Leave every rate blank — the bidder prices it.

ItemDescriptionMake / modelUnitQtySupply rateInstall rateAmountRemarks
1.00[Subsystem or group heading]
1.01[Item, tied to spec clause ...][as specified][No.][ ]
1.02[Item, tied to spec clause ...][as specified][m][ ]
2.00[Next subsystem heading]
2.01[Item ...][as specified][ ][ ]
...............
[Sub-total (ex taxes)]
[Taxes per commercial terms]
[Total]

Field guide: getting the BOQ right

A BOQ is only as fair as its discipline. A few habits separate a clean tender from a dispute waiting to happen:

  • One item per line. Each distinct thing gets its own row. Bundling "cameras and cabling" into a single line hides scope and makes bids incomparable.
  • Clear units and quantities. State the unit the rate is quoted against, and make quantities trace back to the equipment schedule cell for cell. If the schedule says 18 cameras, the BOQ says 18.
  • Separate supply and install. Two columns, always. It exposes padding and makes valuing part-complete work possible.
  • Avoid lump sums that hide scope. A single "security system — lump sum" line tells you nothing and cannot be compared. Break it down.
  • Use provisional sums where scope is genuinely unclear. When something cannot yet be quantified, carry a clearly labelled provisional sum in Remarks rather than a fake precise quantity — and say it will be re-measured.
  • Handle taxes per your commercial terms. Decide once whether rates are exclusive or inclusive of GST, state it, and keep it consistent. Show taxes as their own line.
  • Issue the same BOQ to every bidder. Identical rows and quantities to all. If scope changes mid-tender, issue an addendum to everyone, not a quiet change to one.

A diagram showing one issued BOQ going to three bidders who each return the same rows priced, so their totals are comparable, with a caution that changing the BOQ for one bidder breaks the comparison

Common mistakes

  • Vague descriptions. "CCTV camera" with no reference to the spec invites the cheapest, weakest option. Point the description at the spec clause.
  • Quantities that do not match the schedules. The commonest cause of a mid-project claim. Reconcile the BOQ against the equipment schedule before issue.
  • Hidden scope. Cabling, containment, testing, documentation and spares left out of the BOQ reappear as extras. Give each its own line.
  • Mixing the spec into the BOQ. The BOQ prices; the spec sets quality. Re-writing the spec into descriptions makes both documents drift and contradict each other. Reference, do not repeat.
  • Pricing the rates yourself. The rates are the bidder's offer. Filling them in defeats the tender and the comparison.

How it links to the other documents

The BOQ never stands alone. It is one document in a set that must agree:

  • The equipment and device schedule is the source of the BOQ quantities — reconcile the two before issue.
  • The specification sets the quality behind each description; the BOQ references its clauses rather than repeating them.
  • The tender template issues the BOQ with the commercial and legal terms and the instructions to bidders.
  • The cost planning guide helps you form an internal estimate before tender so you can read the returned bids with judgement, and shows what drives supply and install rates.

For the full set of professional deliverables and how they fit together, see the security resources library and the professional security resources guide.

Completion checklist

Run this before you issue the BOQ:

CheckConfirm
Every item traced to the equipment scheduleQuantities reconciled cell for cell
Descriptions reference the spec, not repeat itNo spec drift
Supply and install kept in separate columnsYes
Preliminaries, cabling, testing, spares and AMC each linedNone buried
No lump sums that hide scopeBroken down
Provisional sums labelled where scope is unclearFlagged in Remarks
Tax treatment stated and consistentPer commercial terms
Identical BOQ prepared for all biddersOne version issued
Commercial and legal review doneBefore issue

Key takeaways

  • The BOQ is the priced, itemised list that lets you tender a security system, compare bids like-for-like and set the contract sum. It sits between the schedules and spec upstream and the tender downstream.
  • Keep the columns disciplined — item, description, make, unit, quantity, supply rate, install rate, amount, remarks — and add preliminaries, cabling and containment, testing and commissioning, and a spares or AMC line.
  • Leave the rates blank. They are the bidder's offer; you fill quantities, they fill prices.
  • Issue one identical BOQ to every bidder so the comparison is fair, and re-issue an addendum to all if scope changes.
  • This is a template to adapt, not contractual wording — get commercial and legal review, and never publish fabricated prices, makes or standards. The rates are the bidder's.

References

  • Your project's own equipment schedule and specification — the authoritative source for the BOQ quantities and the quality behind each description; reconcile against them before issue.
  • Your organisation's procurement and commercial terms — the authoritative source for tax treatment, provisional sums, measurement rules and how the priced BOQ becomes the contract sum; get commercial and legal review.
  • Bureau of Indian Standards catalogue for any standard referenced by your specification; verify the current edition at https://www.services.bis.gov.in/

This is an educational, ready-to-adapt template, not contractual, commercial or legal advice. A BOQ forms part of a procurement contract — engage qualified commercial, procurement and legal professionals before issuing or awarding, and defer specifics to your project and terms.

Export this guide