
Resource Planning — Cost & Resources
The cost slope, the optimum duration, and levelling vs smoothing.
Time costs money two ways at once. Direct cost rises when you compress an activity; indirect cost rises the longer the project runs — so total cost is U-shaped, with an optimum least-cost duration. Learn the cost slope, crashing the network to that optimum, and updating with actuals; then resource allocation, resource smoothing (within float, deadline fixed) and resource levelling (to a limit, deadline may move).
Learning objectives
By the end of this lesson, you will be able to — mapped to the course outcomes for Project Management:
Distinguish direct, indirect and total project cost and the optimum-duration curve.
Compute the cost slope and crash the network for least cost.
Update a schedule with actual progress data.
Tell resource smoothing from resource levelling and apply each.
The cost model & crashing
Add the falling direct cost to the rising indirect cost and the total is U-shaped; crash the cheapest-slope critical activity toward the bottom of that U — and stop at the optimum.[1, 3]
Two costs, one curve
DIRECT cost is tied to activities — labour, material, plant; it FALLS as you allow more time (normal working) and RISES when you compress (overtime, extra crews, premiums). INDIRECT cost is overheads, supervision, site establishment and finance — roughly PROPORTIONAL to duration, so it RISES the longer the job runs. Add them and TOTAL project cost is U-SHAPED against duration. The bottom of that U is the OPTIMUM (least-cost) DURATION.[1]
Resources — smoothing & levelling
Resources are finite and their demand peaks; smoothing shaves the peaks within float without moving the deadline, while levelling caps demand at a limit and may extend the duration.[1, 2]
Finite crews and cranes
Network analysis assumes resources are available when the logic wants them — but crews, cranes, formwork and money are FINITE. RESOURCE ALLOCATION assigns the limited resources to activities, and the demand often PEAKS uncomfortably (everything wants the same crane in week 6). The aggregated demand over time is the RESOURCE HISTOGRAM; the goal of the next two techniques is to tame its peaks.[1]
At a glance
| Aspect | Smoothing | Levelling |
|---|---|---|
| What is fixed | Smoothing: the project end date | Levelling: the resource limit |
| Constraint type | Smoothing: time-constrained | Levelling: resource-constrained |
| Uses | Smoothing: only activities' float | Levelling: may delay any activity |
| Effect on duration | Smoothing: none | Levelling: may extend it |
| Goal | Smoothing: even out peaks | Levelling: stay under the cap |
Key terms
Activity costs (rise when crashed) / time-proportional overheads (rise with duration).
Direct + indirect; U-shaped against duration, minimum at the optimum duration.
(Crash − normal cost) / (normal − crash time): rupees per day of compression.
Deliberately shortening activities, cheapest-slope-first, to reduce project time.
Reschedule within float to even out demand; the end date is unchanged.
Schedule to a resource limit; the project duration may extend.
Studio task
A three-activity chain A → B → C has normal times 8, 6, 5 days and normal costs ₹6,000, ₹4,000, ₹3,000; crash times 6, 4, 3 days and crash costs ₹7,000, ₹4,600, ₹4,200. Indirect cost is ₹400/day. Compute each cost slope, decide which activity to crash first, and find the optimum (least-cost) duration and its total cost. Explain in one line why you stop where you do.
Self-assessment
1. As a project's duration is shortened by crashing, INDIRECT cost generally —
2. The cost slope of an activity equals —
3. Resource LEVELLING differs from smoothing because it —
Recap
References & further reading
- [1]B.C. Punmia & K.K. Khandelwal, Project Planning and Control with PERT and CPM — cost model, cost slope, crashing, levelling.
- [2]PMI, PMBOK Guide & Practice Standard for Scheduling — resource smoothing vs levelling.
- [3]J.D. Wiest & F.K. Levy, A Management Guide to PERT/CPM — time–cost trade-off and optimum duration.
- [4]K.K. Chitkara, Construction Project Management — updating and resource management in Indian practice.
Further reading
- B.C. Punmia & K.K. Khandelwal — Project Planning and Control with PERT and CPM.
- K.K. Chitkara — Construction Project Management.
- J.D. Wiest & F.K. Levy — A Management Guide to PERT/CPM.
Sources gathered and fact-checked June 2026. Published values vary by source, sample and method — treat as indicative and confirm against the cited standard before structural use.
