
Contract Administration & Cost Control
Bills, variations, EOT — and Earned Value Management.
From award to completion the administrator runs a recurring payment cycle — work is measured, the contractor submits a running-account (RA) bill, the Engineer certifies, the owner pays. Learn variations / change orders and their valuation, extension of time (EOT) and prolongation (EOT ≠ money), price escalation, retention and mobilisation advance, the defects-liability period and final account; and cost control via Earned Value Management — PV, EV, AC, the CPI and SPI indices, and EAC. Try the live earned-value calculator.
Learning objectives
By the end of this lesson, you will be able to — mapped to the course outcomes for Project Cost & Contract Management:
Run the RA-bill payment cycle and value variations / change orders.
Distinguish EOT (time) from prolongation cost (money), and apply escalation/retention.
Compute and interpret the EVM metrics — PV, EV, AC, CV, SV, CPI, SPI, EAC.
Explain the defects-liability period and the final account.
Administering the contract
The payment cycle is measure → bill → certify → pay; variations are valued by a rate hierarchy; and an EOT extends time and relieves LDs — but money follows only for compensable delay.[3, 4]
Measure → bill → certify → pay
Once live, the administrator runs a recurring cycle: work is executed → MEASURED (jointly, in the Measurement Book) → the contractor submits a RUNNING ACCOUNT (RA)/interim bill → the Engineer VALUES and CERTIFIES the amount due → the owner PAYS within the contractual period, less retention and recovery of advances. Certification is the legal TRIGGER for payment; timely certificates protect the contractor's cash flow (it funds work ahead of payment — recall the S-curve).[3, 4]
Cost control — Earned Value
EVM integrates scope, time and cost: PV/EV/AC give CV, SV, CPI, SPI and EAC — and spend (AC) is not progress (EV).[1, 2]
PV, EV, AC
Earned Value Management (EVM) integrates scope, time and cost into one measure. PV (Planned Value / BCWS) = budgeted cost of work PLANNED to date. EV (Earned Value / BCWP) = budgeted cost of work ACTUALLY DONE to date. AC (Actual Cost / ACWP) = money ACTUALLY SPENT on that work. MISCONCEPTION→correct: 'if I've spent the budgeted amount on schedule I'm fine' — spending is AC, not progress; you can spend on time yet EARN far less value (low EV). EVM exposes exactly that.[1]
Compute earned value
Move the PV, EV, AC and BAC sliders — the calculator computes CV, SV, CPI, SPI and the forecast EAC, with an on/over-budget and ahead/behind-schedule verdict.
Earned-value calculator · move the sliders
EAC = BAC / CPI = ₹558.82 — the forecast out-turn if current cost performance continues.
CPI/SPI above 1 is good (under budget / ahead); below 1 is the warning. Spend (AC) is not progress (EV).
At a glance
| Aspect | CPI (cost) | SPI (schedule) |
|---|---|---|
| Formula | CPI = EV / AC | SPI = EV / PV |
| Measures | CPI: cost efficiency | SPI: schedule / progress efficiency |
| Value < 1 means | CPI: over budget | SPI: behind schedule |
| Value > 1 means | CPI: under budget | SPI: ahead of schedule |
| Variance partner | CV = EV − AC | SV = EV − PV |
Key terms
Running-account (interim) bill claiming payment for measured work to date.
A formally instructed change to scope/quality/quantity, valued under the variation clause.
A revised completion date for excusable delay, relieving liquidated damages.
Money withheld from payments as performance/defects security, released in stages.
Budgeted cost of work actually performed — progress expressed in money.
Estimate At Completion — the forecast total project cost at finish.
Studio task
Given a project with PV ₹100L, EV ₹85L, AC ₹95L and BAC ₹500L, compute CV, SV, CPI, SPI and EAC, and state in one sentence whether it is over/under budget and ahead/behind schedule. Then explain, with an example, why an EOT for employer-caused delay does not automatically bring extra payment — and what would.
Self-assessment
1. A project shows CPI = 0.9, SPI = 1.05. The project is —
2. An EOT for employer-caused delay entitles the contractor to —
3. Earned Value (EV) equals —
Recap
References & further reading
- [1]PMI, Practice Standard for Earned Value Management & PMBOK Guide — EVM definitions, formulae, indices.
- [2]K.K. Chitkara, Construction Project Management (McGraw Hill, India) — EVM, S-curve, monitoring.
- [3]CPWD Works Manual & GCC — RA bills, MB measurement, retention, mobilisation advance, escalation formula.
- [4]B.S. Patil, Building and Engineering Contracts — variations, EOT, certification, final account (Indian law).
- [5]FIDIC Red/Yellow Book (2017) cl. 8 (time/EOT), cl. 13 (variations), cl. 14 (payment).
Further reading
- PMI — Practice Standard for Earned Value Management.
- K.K. Chitkara — Construction Project Management.
- B.S. Patil — Building and Engineering Contracts.
Sources gathered and fact-checked June 2026. Published values vary by source, sample and method — treat as indicative and confirm against the cited standard before structural use.
