
Claims, Disputes & Resolution
Heads of claim, LD vs penalty (s.74), and the resolution ladder.
A claim asserts an entitlement to more time, more money, or both. Learn the heads of claim (delay, disruption, variation, loss & expense) and how contemporaneous records substantiate them; the India-specific liquidated-damages-vs-penalty distinction (Section 74 abolishes the divide); risk identification and allocation; the dispute-resolution ladder (negotiation → mediation → conciliation → DAB → arbitration → litigation); arbitration under the Arbitration & Conciliation Act 1996; contract closure; and the architect's ethics as an impartial certifier.
Learning objectives
By the end of this lesson, you will be able to — mapped to the course outcomes for Project Cost & Contract Management:
Identify the heads of claim and how contemporaneous records substantiate them.
Explain liquidated damages vs penalty — and the India-specific Section 74 position.
Apply risk allocation and the tiered dispute-resolution ladder, including arbitration.
Uphold the architect's impartial, ethical duty and close the contract.
Claims & liquidated damages
Claims need entitlement, causation and quantum — proven by contemporaneous records; and in India, Section 74 caps liquidated damages at reasonable compensation, with some loss to be shown.[2, 3, 6]
Time, money, or both
A CLAIM asserts an entitlement to more time and/or money. The heads: DELAY (entitlement to EOT for excusable delay); DISRUPTION (loss of productivity even without overall delay — work made harder/slower); VARIATION (payment for instructed/constructive change); and LOSS & EXPENSE (extra cost — prolongation, overheads, finance, idle plant — from employer breach/risk). A valid claim needs ENTITLEMENT, CAUSATION and QUANTUM. MISCONCEPTION→correct: 'delay and disruption are the same' — delay affects the completion date; disruption is lost productivity that may cost money WITHOUT changing the end date.[3, 6]
Risk, the resolution ladder & ethics
Allocate risk to whoever manages it best; escalate disputes lowest-rung-first to arbitration (Act 1996); close out the contract; and certify impartially throughout.[1, 3, 5]
To whoever manages it best
Good contracting IDENTIFIES risks (ground, design, weather, price, regulatory, force majeure) then ALLOCATES each to the party BEST ABLE to control, manage or absorb it — the contractor takes workmanship/productivity risk, the employer takes site-access/design (in DBB)/force-majeure risk, some are shared via escalation. Mis-allocating risk to a party who can't manage it just gets priced back into the bid as contingency (or breeds disputes), so good allocation LOWERS total cost.[3]
At a glance
| Aspect | Liquidated damages | Penalty / India s.74 |
|---|---|---|
| Nature | LD: a genuine pre-estimate of loss | Penalty (intl.): a deterrent sum |
| Enforceable? | LD: yes | Penalty: no (English law) |
| India — s.74 | Distinction abolished | Reasonable compensation ≤ named sum |
| Proof of loss (India) | Generally required | Named sum is the ceiling |
| Binding outcome | Arbitration: yes (award) | Mediation/conciliation: no (consensual) |
Key terms
An assertion of entitlement to more time and/or money under the contract.
A contractually fixed sum payable on a specified breach (usually delay).
A sum meant to deter breach, not estimate loss — unenforceable in English law.
A consensual process where a conciliator may propose settlement terms (Part III, Act 1996).
A private, binding dispute-resolution process producing an enforceable award.
Dispute Avoidance/Adjudication Board — a standing panel giving interim-binding decisions.
Studio task
Take a delay scenario and draft a one-page claim outline — its head (delay/disruption/variation/loss & expense), the entitlement, the causation, and the records you'd rely on. Explain how Section 74 of the Indian Contract Act would treat the liquidated-damages clause, and map the dispute up the resolution ladder, naming where arbitration under the Act 1996 would begin.
Self-assessment
1. Under Section 74 of the Indian Contract Act 1872, a sum named as liquidated damages —
2. Which dispute step produces a BINDING, enforceable award?
3. The guiding principle of risk allocation is to place each risk with —
Recap
References & further reading
- [1]The Arbitration and Conciliation Act, 1996 (India), as amended 2015/2019/2021 — arbitration, conciliation, s.34, s.29A.
- [2]The Indian Contract Act, 1872, Section 74 + Fateh Chand v Balkishan Das (1963), ONGC v Saw Pipes (2003), Kailash Nath v DDA (2015).
- [3]B.S. Patil, Building and Engineering Contracts — claims, LDs, arbitration in Indian construction practice.
- [4]FIDIC Conditions of Contract (2017) cl. 20 (claims) & cl. 21 (disputes / DAAB).
- [5]Council of Architecture, Architects (Professional Conduct) Regulations — impartial certification and ethics; SCL Delay & Disruption Protocol.
Further reading
- B.S. Patil — Building and Engineering Contracts.
- The Arbitration and Conciliation Act, 1996 (bare act with commentary).
- SCL Delay and Disruption Protocol (2nd ed.).
Sources gathered and fact-checked June 2026. Published values vary by source, sample and method — treat as indicative and confirm against the cited standard before structural use.
