Amogh N P
 In loving memory of Amogh N P — Architect · Designer · Visionary 
A construction project-planning desk — a printed Gantt bar chart, a hard hat, rolled drawings and a pen in warm office light: a project being planned, scheduled and controlled.
Unit IProject Management

Introduction to Project Management

Plan, schedule, control — the bar chart, and where CPM and PERT begin.

≈ 40 min + studio task

A project is a temporary, unique endeavour with a defined start and end — and managing it means making conscious trade-offs between time, cost and quality. Learn the three core functions — planning is what and how, scheduling is when, controlling is monitoring and correcting — and the Gantt bar chart with the one thing it cannot show: dependencies or the critical path. Then meet the networks that fix that, CPM and PERT, and the statistics PERT rests on.

Learning objectives

By the end of this lesson, you will be able to — mapped to the course outcomes for Project Management:

1
CO1 · Understand

Define a project and project management, and state the objectives of PM.

2
CO1 · Understand

Distinguish planning, scheduling and controlling — and the time–cost–quality trade-off.

3
CO1 · Analyse

Explain the bar chart (load and progress charts) with its merits and demerits.

4
CO1 · Understand

Tell CPM from PERT, and the probability basis PERT uses.

What PM is

Plan, schedule, control

A project is squeezed by the iron triangle of scope, time and cost; the manager's craft is to plan the logic, schedule the dates, and control the gap between plan and reality.[1, 2]

Plan, schedule, control PLANNING what & how activities + logic SCHEDULING when durations + dates CONTROLLING monitor + correct feedback loop — correct the plan Planning sets the logic; scheduling sets the dates; controlling closes the loop. They are three different jobs.
DiagramThe three project-management functions — planning, scheduling and controlling in a feedback loop

Temporary, unique, constrained

A PROJECT is a temporary endeavour — a definite start and end — undertaken to create a unique product or result; it is not routine, repeating operations. PROJECT MANAGEMENT is applying knowledge, skills, tools and techniques to project activities to meet the requirements. Every project is squeezed by the TRIPLE CONSTRAINT (the 'iron triangle'): SCOPE/quality, TIME and COST — push one and the others move, so the manager's craft is making those trade-offs consciously, with the client's informed consent.[2]

Bars, loads, progress

The Gantt bar chart

Henry Gantt's time-scaled bars are still the everyday site report — simple, visual and immediate — but the classic bar chart shows no logical links and cannot find the critical path.[1]

The Gantt bar chart wk1wk2wk3wk4wk5wk6 Foundation Frame Services Finishes today Shaded = progress; the dashed line is 'today'. Simple and readable — but it shows no dependency links.
DiagramA Gantt bar chart with a today status line and shaded progress, but no dependency arrows
Two networks

CPM, PERT and the statistics

Both replace the bar chart with a network that carries logic: CPM is deterministic with one duration, PERT is probabilistic with three — and PERT leans on the beta distribution and the central limit theorem.[1, 3, 4]

CPM vs PERT CPM deterministic · activity-oriented one duration per activity a single fixed time DuPont, 1957 · + cost trade-off PERT probabilistic · event-oriented three estimates a, m, b amb US Navy / Polaris, 1958 · gives a probability Developed separately; not interchangeable — though software has largely merged them.
DiagramCPM is deterministic with one duration; PERT is probabilistic with three estimates and gives a probability of meeting a date

Two answers to scheduling

Both replace the bar chart with a NETWORK that shows logic. CPM (Critical Path Method, DuPont & Remington Rand, 1957) is DETERMINISTIC and activity-oriented: one duration per activity, and a built-in time–cost trade-off (crashing). PERT (Programme Evaluation & Review Technique, US Navy/Booz Allen for Polaris, 1958) is PROBABILISTIC and event-oriented: THREE time estimates per activity to handle uncertainty, giving the PROBABILITY of meeting a date. MISCONCEPTION→correct: 'PERT and CPM are the same / interchangeable' — they were developed separately and differ in exactly this way, though modern software has largely merged them.[1, 3]

Interactive

Estimate a completion probability

From three estimates per activity, compute the expected time and variance, then slide the target date to read the probability of finishing on time off the normal curve — and see why the expected date is only a 50% promise.

PERT · three estimates & the probability of meeting a date

Actambtₑσ²
A24640.444
B351362.778
C12320.111
D461472.778
E25851
Σ247.111

tₑ = (a + 4m + b) / 6 · σ² = ((b − a) / 6)² · all five activities lie on the critical path.

Expected Te24 d
σ (SD)2.667 d
Z = (Ts − Te)/σ1.5
P(finish ≤ Ts)93.3%

At Ts = Te the chance is ~50%. Te is the mean, not a promise — you need Z and σ to state a confidence level.

CPM vs PERT

At a glance

AspectCPMPERT
Time estimateCPM: one (deterministic)PERT: three — a, m, b (probabilistic)
OrientationCPM: activity-orientedPERT: event-oriented (originally)
OriginCPM: DuPont, 1957PERT: US Navy / Polaris, 1958
Best forCPM: known, repetitive workPERT: novel / uncertain work
GivesCPM: a fixed date + cost trade-offPERT: a probability of meeting a date
Vocabulary

Key terms

Project

A temporary, unique endeavour with a defined start and end — not routine operations.

Triple constraint

Scope/quality, time and cost — the 'iron triangle' every project trades off.

Planning vs scheduling

Planning = what/how/logic; scheduling = when (durations and dates).

Bar (Gantt) chart

Time-scaled horizontal bars; simple, but shows no dependencies or critical path.

Load chart

A bar chart of a resource's commitment over time — to spot over/under-loading.

CPM / PERT

Deterministic critical-path method / probabilistic three-estimate technique.

Apply it

Studio task

Take a small renovation you know (a kitchen, a shop fit-out). List eight activities, then draw a Gantt bar chart for it — and beside it, write down the dependencies the bar chart cannot show (which activity must finish before which can start). In two sentences, explain why those hidden links are exactly what a network diagram exists to capture.

Check your understanding

Self-assessment

1. Which task does the CLASSIC bar (Gantt) chart NOT do?

2. PERT differs from CPM mainly because it —

3. In project management, scheduling —

In a nutshell

Recap

A project is temporary and unique; PM trades off the iron triangle of time, cost and quality consciously.
Planning is what/how, scheduling is when, controlling is monitor-and-correct — they are different jobs.
The Gantt bar chart (with load and progress charts) is simple but shows no dependencies or critical path.
CPM is deterministic and activity-oriented; PERT is probabilistic with three estimates per activity.
PERT rests on the beta distribution and the central limit theorem; Te is the mean (≈50% chance), not a promise.
The evidence

References & further reading

  1. [1]B.C. Punmia & K.K. Khandelwal, Project Planning and Control with PERT and CPM (Laxmi Publications) — the standard Indian text.
  2. [2]PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide) — definitions, the triple constraint.
  3. [3]J.D. Wiest & F.K. Levy, A Management Guide to PERT/CPM (Prentice Hall) — CPM vs PERT origins and method.
  4. [4]K.K. Chitkara, Construction Project Management (McGraw Hill, India) — Indian-context planning, scheduling, control.

Further reading

  • B.C. Punmia & K.K. Khandelwal — Project Planning and Control with PERT and CPM.
  • K.K. Chitkara — Construction Project Management.
  • PMI — PMBOK Guide.

Sources gathered and fact-checked June 2026. Published values vary by source, sample and method — treat as indicative and confirm against the cited standard before structural use.