
Analysis of Rates
Building a rate from materials, labour, overheads — and contractor's profit.
The rate of an item is the price per unit used in the estimate. Rate analysis builds that rate up from its constituents for a defined quantity of work — 1 m³ of brickwork, 100 m² of plaster — by quantifying the materials, the labour and the plant, then adding overheads and contractor's profit (~15% together). Learn the components, the out-turn and lead/lift that fix the coefficients, the standard data in the CPWD Analysis of Rates and DSR, and how the dry-volume factor builds a rate. Try the rate-analysis explorer.
Learning objectives
By the end of this lesson, you will be able to — mapped to the course outcomes for Estimation and Specification:
Explain what rate analysis is and the unit of analysis.
Build a rate from materials, labour, plant, overheads and profit.
Use out-turn, lead/lift and the dry-volume factor to derive coefficients.
Reference the CPWD Analysis of Rates / DSR for coefficients and rates.
The components of a rate
A rate = materials + labour + plant (the prime cost) + ~15% overheads & profit; coefficients come from the dry-volume factor and the schedule of rates.[2, 3]
Build the rate up
The rate is the price per unit (per m³, m², m, No.) used in the estimate. Rate analysis builds it up from its constituents for a defined unit of analysis (e.g. 1 m³ brickwork). Essential whenever no published schedule rate fits, when prices change, or to check a tendered rate.[1, 2]
Build a rate live
Pick an item and see its rate built up from materials and labour (the prime cost) plus overheads and profit.
Rate analysis · pick an item
Brickwork, CM 1:6
per 1 m³| Bricks | ~500 nos × ₹8.00 | ₹4,000 |
| Cement | 1.88 bags × ₹400 | ₹752 |
| Sand | 0.391 m³ × ₹1,800 | ₹704 |
| Labour | mason + mazdoor + bhisti | ₹1,480 |
| Prime cost | ₹6,936 | |
| Overheads & profit @ 15% | ₹1,040 | |
| Rate per 1 m³ | ₹7,976 | |
Illustrative coefficients (DSR-type) and assumed market rates — the rate = prime cost + ~15% overheads & profit.
Worked rate analyses
At a glance
| Component | One | The other |
|---|---|---|
| Cement | PCC (1:2:4): ~6.3 bags/m³ | RCC (M20): ~8.0–8.5 bags/m³ |
| Steel | PCC: none | RCC: measured separately (kg) + cut/bend |
| Formwork | PCC: minimal | RCC: significant (m²) added |
| Cement in 1 m³ | 1440 kg | = 28.8 bags (1 bag = 50 kg) |
| Overheads + profit | Profit ~10% | OH + profit together ~15% on prime cost |
Key terms
Building up the unit rate from materials, labour, plant, overheads and profit.
Materials + labour + plant, before overheads and profit are added.
The standard daily output of a worker — fixes the labour coefficients.
Multiplier (~1.52) converting wet mortar/concrete to dry ingredient volume.
The quantity of a material or labour per unit of work.
The Delhi Schedule of Rates / CPWD Analysis of Rates — the standard coefficient & rate source.
Studio task
Prepare a full rate analysis for 1 m³ of brickwork in CM 1:6: work the dry mortar volume (× 1.52), the cement (in bags) and sand, the bricks (~500), and the labour from out-turn, then add water and 15% overheads & profit to reach the rate. Quote your coefficients from a schedule of rates and state how the rate would change for CM 1:4.
Self-assessment
1. The number of cement bags in 1 m³ is —
2. The dry volume of ingredients for mortar/concrete is taken as ___ × the wet volume.
3. Overheads + contractor's profit are commonly added at about —
Recap
References & further reading
- [1]B.N. Dutta, Estimating and Costing in Civil Engineering (rate-analysis chapter, worked items).
- [2]M. Chakraborti, Estimating, Costing, Specification & Valuation (analysis of rates).
- [3]CPWD, Analysis of Rates (DAR) and Delhi Schedule of Rates (DSR) — coefficients & rates.
- [4]S.C. Rangwala, Estimating and Costing (out-turn & task-work data).
- [5]BIS, IS 1200 (the measurement basis underlying the unit of analysis).
Further reading
- B.N. Dutta — Estimating and Costing in Civil Engineering.
- CPWD — Analysis of Rates / DSR.
- S.C. Rangwala — Estimating and Costing.
Sources gathered and fact-checked June 2026. Published values vary by source, sample and method — treat as indicative and confirm against the cited standard before structural use.
